सार्वजनिक निकाय
Department of Roads · Division Office, Kathmandu
5
In the pipeline
प्रक्रियामा
रु ४३.१ क
Estimated this year
अनुमानित
4
Awaiting a decision
निर्णय पर्खाइमा
रु ३१ क
Budget unobligated
बाँकी बजेट
12
Running contracts
चालु सम्झौता
Pipelineप्रक्रिया
| Procurement | Estimate | Stage | Days in stage | Checks |
|---|---|---|---|---|
| Nagdhunga–Naubise section 3 | रु २४.० क | Award | 11 | clear |
| Kalanki drainage, package 1 | रु ८.६ क | Draft tender | 4 | 2 blocking |
| Ring road lighting | रु ३.४ क | Evaluation | 26 | over 21 days |
| Bridge maintenance, 4 sites | रु ६.२ क | Published | 9 | clear |
| Office vehicles (2) | रु ९० ल | Planned | — | not in plan |
जाँच · ChecksWhat is checked →
⚠Ring road lighting has been in evaluation 26 days; the Act expects 21.Regulation 2064 r.68. Two members have not marked since 2082-06-28.
✖Office vehicles (2), रु ९० लाख, is not in the approved annual plan.Regulation 2064 r.7.
⚠64% of last year’s contract value was signed in the final two months.रु ४२ करोड of रु ६६ करोड in Jestha and Ashadh.
✔Budget line 3.6.1.14 holds रु ३१ करोड unobligated — LMBIS, 2082-06-30.
Advisory. Checks decide nothing.
Awaiting a decisionनिर्णय पर्खाइमा
Nagdhunga–Naubise section 3 — award for signatureEvaluation report signed by all three members 2082-08-03chief of the entity
Kalanki drainage, package 1 — tender awaiting approvalDrafted by Deepak Thapa; 2 blocking checks openchief of the entity
Running bill 3, Hetauda bypass — paymentSite engineer certified 52% progressaccounts
Annual procurement plan, second trimesterDue 2082-07-30 under Reg. 2064 r.7procurement officer
This officeकार्यालय
Chief: Er. Sabita Adhikari
Procurement officer: Deepak Thapa
Accounts: Maya Lama
Administrator: Deepak Thapa
Drafting and approval are separate accounts; the system refuses both on one procurement.