| Bidder | Bid amount | vs estimate | Status |
|---|---|---|---|
| Siddhi Construction Pvt. Ltd.Kathmandu · Class A | रु २२,५०,००,००० | −6.2% | Awarded |
| Himal Nirman SewaLalitpur · Class A | रु २३,१०,००,००० | −3.7% | Evaluated |
| Gandaki BuildersPokhara · Class A | रु २४,८०,००,००० | +3.3% | Non-responsive |
| Everest JVKathmandu · Class A | रु २५,२०,००,००० | +5.0% | Non-responsive |
| Koshi NirmanBiratnagar · Class A | रु २५,९०,००,००० | +7.9% | Evaluated |
| Tribeni ConstructionButwal · Class A | रु २६,४०,००,००० | +10.0% | Non-responsive |
| Annapurna NirmanChitwan · Class A | रु २७,१०,००,००० | +12.9% | Non-responsive |
Evaluation: lowest substantially responsive bid. Opened 2082-07-14 at 14:00 before the representatives of four bidders; every amount was read out aloud.
| Signed value | रु २२,५०,००,००० |
| Variations approved | + रु १,१०,००,००० (+4.9%) |
| Final value | रु २३,६०,००,००० |
| Paid to date | रु १४,००,००,००० (59%) |
| Start / due | 2082-08-20 / 2083-06-30 |
Physical progress
52% as certified by the site engineer, 2083-01-30
Financial progress
Two running bills paid, one in process
Variation 1 — rock excavation beyond the bill of quantities
Approved 2083-01-12 · + रु १,१०,००,००० · justification (PDF)
Check: the varied item is the one this bidder priced 38% below the district median at bid stage. The same pattern appears in 6 of this supplier’s 41 contracts.
To Siddhi Construction at रु २२,५०,००,०००, as the lowest evaluated bid. Any other bidder may complain to the public entity within the time the Act allows.
Seven bids opened at 14:00; four bidders sent representatives. All amounts were read out and published the same evening.
Seven days added; no change to scope. Bid security validity moved with it.
Every notice stays on the procurement it belongs to, permanently.
| Estimated value | रु २४,००,००,००० |
| Awarded value | रु २२,५०,००,००० |
| Against estimate | −6.2% |
| Bidders | 7 |
| Method | NCB · single-stage, two-envelope |
| Source of funds | Government of Nepal |
| Budget line | 3.6.1.14 ↗ |
| Published | 2082-06-12 |
| Closed | 2082-07-14, 12:00 |
| Opened | 2082-07-14, 14:00 |
| Award decision | 2082-08-03 |
| Process ID | ocds-np-00412987 |
This page is the whole procurement: the plan entry it came from, the tender as published, the award, the contract and every payment under it. It keeps its address for good, including after the work is finished.
The tender as bidders saw it · the annual plan · all contracts · this supplier