मूल्याङ्कन समिति · all evaluations
Upgrading of Nagdhunga–Naubise road, section 3
DoR/NCB/W/2082-83/14 · opened 2082-07-14 at 14:00 before four bidders’ representatives · seven bids · committee of three
| Bidder | Letter of bid | Bid security | Audited accounts | Similar works | Equipment and personnel | Arithmetic | Committee |
|---|---|---|---|---|---|---|---|
| Siddhi Construction Pvt. Ltd.Kathmandu · Class A · रु २२,५०,००,००० | ✔ | ✔ | ✔ | ✔ | ✔ | ✔ | responsive |
| Himal Nirman SewaLalitpur · Class A · रु २३,१०,००,००० | ✔ | ✔ | ✔ | ✔ | ✔ | ✔ | responsive |
| Gandaki BuildersPokhara · Class A · रु २४,८०,००,००० | ✔ | ✔ | ✖ missing | ✔ | ✔ | ✔ | non-responsive |
| Everest JVKathmandu · Class A · रु २५,२०,००,००० | ✔ | ⚠ 112 days | ✔ | ✔ | ✔ | ✔ | to decide |
| Koshi NirmanBiratnagar · Class A · रु २५,९०,००,००० | ✔ | ✔ | ✔ | ⚠ 1 of 2 | ✔ | ✖ +रु ४.२ ल | to decide |
| Annapurna NirmanChitwan · Class A · रु २७,१०,००,००० | ✔ | ✖ missing | ✔ | ✔ | ✔ | ✔ | non-responsive |
| Tribeni ConstructionButwal · Class A · रु २६,४०,००,००० | ✔ | ✔ | ✔ | ✖ none | ✔ | ✔ | non-responsive |
Every mark was pre-filled by reading the bids and is editable — click a cell to change it, and the change records who made it and when. The committee’s mark governs; the opening minutes and each bid’s documents are one click away.
| Bidder | Read out | Arithmetic correction | Evaluated price | vs estimate | Rank |
|---|---|---|---|---|---|
| Siddhi Construction | रु २२,५०,००,००० | — | रु २२,५०,००,००० | −6.2% | 1 · lowest evaluated |
| Himal Nirman Sewa | रु २३,१०,००,००० | — | रु २३,१०,००,००० | −3.7% | 2 |
| Everest JV | रु २५,२०,००,००० | — | रु २५,२०,००,००० | +5.0% | 3 · security short |
| Koshi Nirman | रु २५,९०,००,००० | + रु ४,२०,००० | रु २५,९४,२०,००० | +8.1% | 4 · correction refused? |
| Tribeni Construction | रु २६,४०,००,००० | — | — | +10.0% | not evaluated |
| Gandaki Builders | रु २४,८०,००,००० | — | — | +3.3% | not evaluated |
| Annapurna Nirman | रु २७,१०,००,००० | — | — | +12.9% | not evaluated |
Only substantially responsive bids are evaluated. ITB 31 allows the employer to correct arithmetic; a bidder who refuses the correction forfeits the bid security.
Bid by bid
Draft evaluation report
Nine pages in the standard format, every conclusion linked to the page of the bid it came from. Four bids non-responsive; the lowest evaluated responsive bid recommended at रु २२,५०,००,०००, which is 6.2% below the estimate.
| Recommendation | Amount | Ground |
|---|---|---|
| Award to Siddhi Construction Pvt. Ltd. | रु २२,५०,००,००० | Lowest evaluated substantially responsive bid, ITB 33 |
| Second ranked, if the first declines | रु २३,१०,००,००० | Himal Nirman Sewa |
| Member | Marked | Signed |
|---|---|---|
| Er. Sabita Adhikari — chair | 6 of 6 | — |
| Deepak Thapa | 6 of 6 | — |
| Maya Lama — accounts | 2 of 6 | — |
The report cannot be signed until all three members have marked every requirement, and it is not a recommendation until all three sign with their tokens. It then goes to the chief of the entity, who awards or returns it with reasons.
Open the draft Download as DOCX Remind Maya Lama